Raw Material Inventory Control Analysis Using the Material Requirement Planning Method at Donat Brownies in Solo

Authors

  • Nadya Galuh Ami Seno Universitas Slamet Riyadi Surakarta
  • Sunarso Sunarso Universitas Slamet Riyadi Surakarta

DOI:

https://doi.org/10.54065/ijed.6.2.2026.878

Keywords:

Economic Order Quantity (EOQ), Inventory Control, Lot For Lot (LFL), Raw Material Procurement, Requirement Planning (MRP), Period Order Quantity (POQ), Raw Materials

Abstract

Donat Brownies is a micro, small, and medium enterprise (MSME) operating in the food industry, specifically producing donuts and brownies. Currently, the business manages its raw material inventory manually or relies on intuitive estimation when procuring supplies. This study aims to analyze the efficiency of raw material inventory control. The research employs the Material Requirements Planning (MRP) method, utilizing the Lot-for-Lot (LFL), Economic Order Quantity (EOQ), and Period Order Quantity (POQ) techniques for data analysis. The data required includes a general overview of Donat Brownies, the production process, and figures regarding raw material usage, procurement, ordering costs, and holding costs. Data collection was conducted through interviews. Based on the calculations, the total cost under Donat Brownies current policy is Rp935,011. In contrast, the total costs using MRP techniques are Rp256,548 for Lot For Lot (LFL), Rp441,751 for Economic Order Quantity (EOQ), and Rp441,765 for Period Order Quantity (POQ). Consequently, the researcher concludes that the Lot For Lot (LFL) method is the most efficient approach for Donat Brownies.

References

Abdullah, R., & Suseno. (2024). Efficiency strategy for procurement of raw materials for side beam for bogie with Material Requirement Planning at PT XYZ. Jurnal Sistem Teknik Industri, 26(2), 218–227. https://doi.org/10.32734/jsti.v26i2.16402

Aditama, D., Nurainun, T., Lubis, F. S., Nofirza, N., & Anwardi, A. (2026). Controlling the inventory of boiler ash raw materials in organic fertilizer using the Minmax method (Case study: UMTR Belilas Organic Fertilizer). IJIEM – Indonesian Journal of Industrial Engineering and Management, 7(1), 14–22. https://doi.org/10.22441/ijiem.v7i1.31728

Ama, Z. H., Soebagiyo, D., & Andriyani, N. (2024). The role of human resources development (HRD) in increasing the competitive advantage of Brownies Cinta employees (PT Berkah Ridho Cinta Indonesia). Income Journal of Economics Development, 4(1), 1–14. https://doi.org/10.54065/ijed.4.1.2024.204

Ardyani, A. D., & Donoriyanto, D. S. (2025). Optimizing the inventory fulfillment level of store goods from PT. XYZ warehouse with the application of response surface methodology. Operations Excellence: Journal of Applied Industrial Engineering, 17(3), 299–307. https://doi.org/10.22441/oe.2025.v17.i3.154

Arijuddin, M. N., Rahayu, S., & Riandani, A. P. (2026). Optimizing toluene inventory control using Economic Order Quantity. ENERGY: Jurnal Ilmiah Ilmu-Ilmu Teknik, 16(1), 178–194. https://doi.org/10.51747/energy.v16i1.16112

Arsydi, M. D., & Nuryana, I. K. D. (2025). Design and development of raw material inventory system for “Es Barbar” SME using the Material Requirement Planning method. Journal of Emerging Information Systems and Business Intelligence (JEISBI), 6(3), 384–398. https://doi.org/10.26740/jeisbi.v6i3.65777

Aulia, R. D., Akin, Y., & Putri, W. (2026). Analysis of elementary students’ participation levels in hockey extracurricular activities. ACTIVE: Journal of Physical Education, Sport, Health and Recreation, 15(2), 1011–1017. https://doi.org/10.15294/active.v15i2.49742

Azim, M. I., Mulyani, H., Mardiani, R., & Aliefia, A. Y. (2026). Optimising inventory cost efficiency through the Economic Order Quantity (EOQ) model. Jurnal Pendidikan Akuntansi & Keuangan, 14(1), 120–131. https://doi.org/10.17509/jpak.v14i1.96061

Baroroh, I., Tarigan, E. F., Sumantri, S. H., Azhar, A., Hardianto, D., & Kristiyono, T. A. (2025). Implementation of material control in tugboat ship building using the Lot for Lot (LFL) method case study: (PT.PMP). International Journal of Marine Engineering Innovation and Research, 9(3), 408–416. https://doi.org/10.12962/j25481479.v9i3

Br Siahaan, E. H., & Lubis, R. S. (2025). Probabilistic model of back order policy on Dodol Pulut raw material inventory control with linear programming. KUBIK: Jurnal Publikasi Ilmiah Matematika, 10(1), 87–97. https://doi.org/10.15575/kubik.v10i1.49121

Chalid, A., & Handayani, W. (2025). Reduction of raw material inventory costs with an operational management approach for beverage products at Loca Coffee. International Journal of Business and Applied Economics, 4(1), 53–68. https://doi.org/10.55927/ijbae.v4i1.13128

Dewi, P. A., Rum, M., & Amril. (2026). Analysis of production cost control for determining selling prices at UD. Mansur Furnitur. Income Journal of Economics Development, 6(2). https://doi.org/10.54065/ijed.6.2.2026.839

Fauziah, R., Pinto, M. N., & Lusiana, L. (2026). Material Requirements Planning (MRP) in the implementation of minimarket inventory stock control. Jurnal Manajemen dan Profesional, 7(2), 324–331. https://doi.org/10.32815/jpro.v7i2.3052

Haryono, F. R. Z., Sihombing, A. M., Prabawati, I., & Suprapto, F. A. (2026). MSMEs as a driving motor for decent work towards a sustainable Indonesian economy. Income Journal of Economics Development, 6(1), 89–96. https://doi.org/10.54065/ijed.6.1.2026.743

Imansuri, F., Ikhsanjani, A. M., Sumasto, F., Dendra, F. G., Suroso, F., & Rozi, M. F. (2025). Application of Material Requirement Planning in bracket chamber production: A case study of automotive component company. IJIEM – Indonesian Journal of Industrial Engineering and Management, 6(1), 119–127. https://doi.org/10.22441/ijiem.v6i1.26305

Indriarti, W., Suharto, & Harri, M. (2025). The effect of work experience and incentives on employee performance with motivation as a mediating variable at Bank Mandiri Gambir Branch. Krisnadwipayana International Journal of Management Studies, 5(2), 116–134. https://doi.org/10.35137/kijms.v5i2.954

Isnataeni. (2023). Income analysis of micro small to medium enterprises (UMKM) coffee processing center in the District Bantaeng (Newn case study Banyorang Tompobulu Anxiety). Income Journal of Economics Development, 3(2). https://garuda.kemdiktisaintek.go.id/documents/detail/4585153

Jasunda, B. A. A., & Atristyanti, I. G. (2026). Analysis of inventory control using the EOQ (Economical Order Quantity), LFL (Lot For Lot), and POQ (Period Order Quantity) methods for cost optimization (A study on warehouse goods at PT Eco Baby Indonesia). Business, Economics, Law, Communication, and Social Sciences, 2(2), 215–229. https://doi.org/10.66755/belacoss.v2i2.182

Kisty, T. A. H., Safitri, E., Basriati, S., & Soleh, M. (2025). Application of Economic Production Quantity (EPQ) method and Just in Time method (JIT) in bread raw material inventory control. Zeta – Math Journal, 10(1), 30–38. https://doi.org/10.31102/zeta.2025.10.1.30-38

Kusuma, K. R., Helmyawan, S. W., Fanida, E. H., & Hidayat, M. F. (2026). Analysis of regional expenditure efficiency in the management of the Tuban Regency budget during the Covid-19 pandemic. Income Journal of Economics Development, 6(2), 134–143. https://doi.org/10.54065/ijed.6.2.2026.701

Lubis, M. S., Nurlaila, & Nurbaiti. (2026). Implementation of lean management in reducing waste and increasing productivity of intercity bus transportation PT. RAPI. Jurnal Manajemen Bisnis, 13(1), 219–233. https://doi.org/10.33096/jmb.v13i1.1406

Mangkona, F. A., Wahyuda, W., & Sitania, F. D. (2026). Analysis of raw material inventory control in the Amplang production process (Case study: UD Taufik Jaya Makmur). IJIEM – Indonesian Journal of Industrial Engineering and Management, 6(3), 402–415. https://doi.org/10.22441/ijiem.v6i3.31071

Meihani, N. R., Nayla, F. N. R., Aulia, R., Zayyan, K. Z. S., Meirinawati, & Oktariyanda, T. A. (2026). MSME empowerment management through the E-Peken program in an effort to improve the local economy in Surabaya. Income Journal of Economics Development, 6(2), 97–105. https://doi.org/10.54065/ijed.6.2.2026.744

Mendrofa, S. D., Zebua, S., Mendrofa, M. S. D., & Gea, J. B. I. J. (2025). Production optimization through the Material Requirement Planning (MRP) method in the Nias tofu product business in Onomamolo Village I Lot. Economics and Business Journal (ECBIS), 4(1), 139–152. https://doi.org/10.47353/ecbis.v4i1.265

Nasution, A. S., Simbolon, O. B., Muliawati, T., Edriani, T. S., Noor, D. M. M., & Fauzi, R. (2025). Raw material inventory control using the Period Order Quantity (POQ) method to reduce stockout and overstock risks. Vygotsky: Jurnal Pendidikan Matematika dan Matematika, 7(2), 97–110. https://doi.org/10.30736/voj.v7i2.1163

Nomianta, B., & Yoga, T. (2026). Raw material inventory planning using the MRP (Material Requirement Planning) method for potato chips products (Case study of CV. Cita Mandiri, Batu City, East Java). Jurnal Hexagro, 10(1), 1–10. https://doi.org/10.36423/hexagro.v10i1.881

Nursia, & Febrianti, D. (2025). The role of operational management in improving supply chain performance. Jurnal Sinar Manajemen, 12(1), 23–29. https://doi.org/10.56338/jsm.v12i1.7691

Rahmadini, R., Nurainun, T., Hartati, M., Lubis, F. S., & Nur, M. (2026). Analysis of burger main raw material inventory control using the Economic Order Quantity (EOQ) method and the Just in Time (JIT) method. IJIEM – Indonesian Journal of Industrial Engineering and Management, 7(1), 114–126. https://doi.org/10.22441/ijiem.v7i1.31502

Ramadhan, A., & Saifuddin, J. A. (2024). Analysis of raw material inventory control using the Min-Max Stock method to control inventory costs at PT. Artha King Indonesia. IJIEM – Indonesian Journal of Industrial Engineering and Management, 5(2), 529–544. https://doi.org/10.22441/ijiem.v5i2.22293

Rani, H. A., Syammaun, T., Rachman, F., Amin, J., & Mahzarullah. (2025). Optimization of construction material inventory using Material Requirement Planning. Jurnal LINEARS, 8(1), 1–7. https://doi.org/10.26618/j-linears.v8i1.17116

Renata, E. A., Soedarto, T., & Widayanti, S. (2025). Analysis of procurement and supply chain control of sugarcane in a sugar mill. Jurnal Teknik Pertanian Lampung (Journal of Agricultural Engineering), 14(5), 1935–1947. https://doi.org/10.23960/jtepl.v14i5.1935-1947

Ritonga, N. F., Koto, H., & Firmansyah, F. (2026). Inventory control of raw materials by applying the Min-Max method to reduce stockout and overstock in the Al-Batsit Bakery Home Industry. EKOMA: Jurnal Ekonomi, Manajemen, Akuntansi, 5(5), 7760–7767. https://doi.org/10.56799/ekoma.v5i5.17239

Safutra, N. I., Fole, A., Dahlan, M., Hafid, M. F., Ahmad, A., Herdianzah, Y., & Muhtada, A. (2024). Optimizing raw material inventory control for aluminum wardrobes using the Material Requirements Planning (MRP) method: A case study on Amal Jaya SME. Jurnal Sistem Teknik Industri, 26(2), 191–198. https://doi.org/10.32734/jsti.v26i2.15972

Salsabella, E., Lukinita, L., Berlandy, K. A., Aulia, F. H., Meirinawati, & Oktariyanda, T. A. (2026). Implementation of management functions (POAC) in the MSME empowerment program at the Ministry of Cooperatives and Small and Medium Enterprises. Income Journal of Economics Development, 6(1), 49–56. https://doi.org/10.54065/ijed.6.1.2026.706

Sari, I. M., & Rismawati, R. (2025). Inventory optimization analysis using the Economic Order Quantity (EOQ) method at Pabrik Kerupuk Citra. Jurnal Ilmiah Multidisiplin, 4(4), 67–69. https://doi.org/10.56127/jukim.v4i04.2150

Setiawan, R., & Mundari, S. (2026). Optimal raw material planning to minimize out of stock costs using the Material Requirement Planning method. JRSI (Jurnal Rekayasa Sistem dan Industri), 13(1), 123–130. https://doi.org/10.25124/jrsi.v13i01.11131

Setianto, T., Harinie, L. T., Syamsudin, A., & Giovanni, J. (2025). Implementation of Material Requirements Planning for raw material inventory control in home industry Palangka Raya. JURISMA: Jurnal Riset Bisnis & Manajemen, 15(1). https://doi.org/10.34010/ybk4h960

Statistics Indonesia. (2024). Statistical yearbook of Indonesia 2024. https://www.bps.go.id/id/publication/2024/02/28/c1bacde03256343b2bf769b0/statistik-indonesia-2024.html

Sulawati, Darmawansah, & Natsir, U. (2025). Financial decision-making in corporate management: A systematic literature review. Income Journal of Economics Development, 5(2). https://doi.org/10.54065/ijed.5.2.2025.477

Sypriansyah, D., Arfah, M., & Suliawati. (2025). Raw material inventory analysis using the Material Requirement Planning method in the UMKM Ayam Penyet Mandoge Waroeng Kandar Kuphi. Proceeding of International Conference on Science and Technology UISU, 2(5), 170–176. https://doi.org/10.30743/4h42jd75

Vitadiar, T. Z., Prismana, I. G. L. P. E., & Permadi, G. S. (2025). Implementation of a raw material inventory control information system using the Continuous Review System method at Naf’a Bakery. Jurnal Sistem Informasi Bisnis, 15(4), 473–479. https://doi.org/10.14710/vol15iss4pp473-479

Wahyudi, M., Wahyuda, W., & Sitania, F. D. (2025). Inventory planning and control on packaging raw materials in the bottled drinking water business (AMDK) PT XYZ Samarinda City. IJIEM – Indonesian Journal of Industrial Engineering and Management, 5(3), 752–769. https://doi.org/10.22441/ijiem.v5i3.23691

Downloads

Published

2026-10-06

How to Cite

Seno, N. G. A., & Sunarso, S. (2026). Raw Material Inventory Control Analysis Using the Material Requirement Planning Method at Donat Brownies in Solo. Income Journal Of Economics Development, 6(2), 347–362. https://doi.org/10.54065/ijed.6.2.2026.878